Congestion-free Ride To Iim Road Soon | Lucknow News – Times of India



Congestion-free Ride To Iim Road Soon | Lucknow News – Times of India

LUCKNOW: Aimed at easing traffic congestion, the first phase of the Green Corridor project — between IIM Road and Hardinge Bridge (near Daliganj) — is nearing completion.
According to AK Senger, the project director, the first phase of the Green Corridor consists of two parts — a bridge connecting IIM Road and the concrete bridge over the Gomti River, and a six-km-long four-lane road between IIM Road and Hardinge Bridge.
The bridge is set to be completed on Feb 15, while the first layer of bitumen for the road is scheduled to be laid by Feb 19. The entire Phase-I, which costs Rs 150 crore, is expected to be completed within one and a half years.
The project aims to ease traffic congestion from Hardoi Bypass to Old City areas, benefiting residents of LDA’s Basant Kunj and Prabandh Nagar Yojana. Senger estimates that around one lakh people, including employees, businessmen, and residents, will benefit from the improved connectivity to Hazratganj, Kaiserbagh, Nishatganj, and Gomti Nagar.
The new bridge constructed under the Green Corridor is expected to eliminate the need to navigate congested areas like Dubagga, Balaganj intersection, Tahsinganj, and Ghantaghar near Hussainabad. Commuters traveling from Hazratganj, Kaiserbagh, and Khadra towards Basantkunj, Amrapali, Jehta, and Mall will also experience a quicker route. “The completion promises to reduce traffic congestion, improve connectivity, and save valuable time for commuters,” Senger added.
Regarding other phases, he mentioned that the entire Green Corridor project, estimated at Rs 7,500 crore, is planned in four phases. Phase-II will extend from Hardinge Bridge to Pipraghat, Phase-III from Pipraghat to Shaheed Path, and Phase-IV from Shaheed Path to Kisan Path.
Senger mentioned that preliminary detailed project reports (DPRs) for Phases II to IV have been framed.
We also published the following articles recently

Stalin writes to PM for phase-2 approval
Chennai CM M K Stalin seeks PM Narendra Modi’s intervention for the approval of CMRL phase-2 project. The project, recommended by MoHUA and NITI Aayog, has funding tied up from JICA, ADB, AIIB, and NDB. However, CCEA approval has been pending for over two years, causing delays and financial strain.
States first Green Mobility Corridor in Hubballi delayed
The completion of Hubballi’s Green Mobility Corridor is crucial to improve the quality of life and prevent the breeding of infectious diseases in the rajakaluve. The project aims to establish an 11-km non-motorised corridor with various amenities, and the budget for the project is Rs 130 crore.





Source link

Leave a Reply

Discover more from DIGINEWZINDIA

Subscribe now to keep reading and get access to the full archive.

Continue reading